Pla 80 HOV Phase 3

Description: In Placer County. Add HOV Lanes and Aux lanes on Route 80 from Miners Ravine to 1kilometer east of Route 65.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Rocklin, Roseville
Zip Code 95661, 95677, 95678
 
Senate District
01, 04
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
 
County/State Route Placer 80
Postmile Begin/End 2.8 5.1
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  156    993  
Lane Miles Added (HOV)  2.3    4.6  
Peak Period Time Savings (minutes)  10571    67,212  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Jonathan Pray (530) 740-4920   jonathan.pray@dot.ca.gov
Design (PS&E) Phase
Caltrans Jonathan Pray (530) 740-4920   jonathan.pray@dot.ca.gov
Right of Way Phase
Caltrans Jonathan Pray (530) 740-4920   jonathan.pray@dot.ca.gov
Construction Phase
Caltrans Jonathan Pray (530) 740-4920   jonathan.pray@dot.ca.gov
 
Corridor System Management Plan
Caltrans Jeff Pulverman (916) 274-0638   jeff.pulverman@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$31,300 $-8,696 $22,604
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$2,700 $23,689 $26,389
 
Total**** $34,000 $14,993 $48,993

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$2,500 $1,000 $3,500 $2,610
Right of Way
$200 $400 $600 $180
Construction
$31,300 $13,593 $44,893 $30,632
 
Total* $34,000 $14,993 $48,993 $33,422

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2001 

06/01/2004 
 

 
04/01/2001 

06/01/2004 
100  04/01/2001 

06/01/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

12/01/2008 
 

 
07/01/2007 

12/01/2008 
100  07/01/2007 

11/25/2008 


Begin Right of Way Phase

End Right of Way Phase
11/01/2007 

09/01/2009 
 

 
11/01/2007 

09/01/2009 
100  07/02/2007 

10/02/2008 


11 
Begin Construction Phase

End Construction Phase
05/01/2009 

01/01/2011 
 

 
05/01/2009 

01/01/2011 
100  08/10/2009 

06/17/2013 
-3 

-30 
Begin Closeout Phase

End Closeout Phase
01/01/2012 

01/01/2013 
 

 
01/01/2012 

01/01/2013 
75  06/13/2013 

10/01/2017 
-18 

-58 
Corridor System Management Plan
Adoption Date 03/01/2009    03/01/2009   
Implementation Date 07/01/2010    07/01/2010   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 156 993
Lane Miles Added (HOV) 2.3 4.6
Peak Period Time Savings (minutes) 10571 67,212

Bond Funding Cost
Adopted:
$31,300,000
Current Approved:
$22,604,000
Actual Expenditures:
$22,543,000

 

Status as of December 31, 2023.